Antigo Times

Top Menu

  • E-Editions
  • Contact Us

Main Menu

  • News
    • Business
  • Covid 19
  • Opinion
  • Courts
  • Arts & Ent
  • Sports
    • Sports News
    • High School Sports Scores
  • Classifieds
    • View Ads
    • Place Ads
  • Legal Ads
    • Our Legals
    • Statewide
  • Obits
  • Video
  • Best of 2022
  • Class of 2020
  • E-Editions
  • Contact Us

logo

Antigo Times

  • News
    • Business
  • Covid 19
  • Opinion
  • Courts
  • Arts & Ent
  • Sports
    • Sports News
    • High School Sports Scores
  • Classifieds
    • View Ads
    • Place Ads
  • Legal Ads
    • Our Legals
    • Statewide
  • Obits
  • Video
  • Best of 2022
  • Class of 2020
DOTLocal InterestNews
Home›News›DOT›North Central Region Road Construction Update

North Central Region Road Construction Update

By Antigo Times
October 12, 2017
1323
0

The Wisconsin Department of Transportation (WisDOT) provides a weekly update on road construction in north central Wisconsin, which includes: Adams, Green Lake, Florence, Forest, Iron, Langlade, Lincoln, Marathon, Marquette, Menominee, Oneida, Portage, Price, Shawano, Vilas, Waupaca, Waushara, and Wood counties.

Motorists are reminded that using handheld cell phones in Wisconsin work zones is illegal. To learn more about North Central Region transportation news, project updates, studies, and more:

  • Follow us on Twitter: @WisDOTnorthcent
  • Visit the region’s 511 website:  http://projects.511wi.gov/region/north-central/

 

Iron County

 

Highway: WIS 47 (*updated*)

Location: Between Lower Sugar Bush Lane and US 51

Schedule: September 5 to October 31, 2017

Cost: $1.4 million

Description: Improvements include resurfacing the highway and replacing several culverts.

Traffic impacts: WIS 47 will remain open to traffic during construction. Motorists can expect lane closures and flagging operations.

 

Highway: US 51 (*updated*)

Location: Between Weber Road and County C

Schedule: August 16 to October 13, 2017

Cost: $1.6 million

Description: Crews will resurface the highway, replace culverts, and install centerline rumble strips.

Traffic impacts: US 51 will remain open to traffic during construction. Motorists can expect lane closures and flagging operations.

 

Langlade County

 

Highway: US 45 (*updated*)

Location: Between Birch Road and Maple View Road (south of Antigo)

Schedule: September 25 to October 27, 2017

Cost: $1.1 million

Description: Crews will resurface the highway, replace a culvert, upgrade beam guard.

Traffic impacts: The highway will remain open to traffic. Motorists can expect flagging operations and lane closures.  

 

Lincoln County

 

Highway: US 51

Location: Marathon County line to the Oneida County line

Schedule: July 31, 2017 to July 2018

Cost: $992,000

Description: Work includes polymer overlays on eight bridges and erosion protection for piers on four bridges. Crews will also install a new concrete deck overlay to the southbound US 51 bridges over Kaphaem Road. The work in 2018 includes weekday and weekend lane closures before Memorial Day.

Traffic impacts: Motorists can expect weekday lane closures.

 

Marathon County

 

Highway: WIS 52

Location: Wausau to Aniwa

Schedule: June 26 to October 25, 2017

Cost: $1.6 million

Description: Crews will mill and pave the highway from Elm Road to the Eau Claire River.

Website: https://projects.511wi.gov/wis52marathon/

Traffic impacts:

  • Motorists can expect to encounter daytime lane closures and flagging operations.
  • Motorists are reminded to drive with caution as they approach the work site. Watch for turning and/or slow moving trucks or equipment.

 

Highway: US 51

Location: Marathon County WW interchange

Schedule: February 29, 2016 to late October 2017

Cost: $6.32 million

Description: Last year crews replaced the bridge decks on northbound US 51 over Decator Drive and constructed a temporary structure for traffic management. This year crews will replace the bridge decks on northbound and southbound US 51 over County WW

Website: https://projects.511wi.gov/us51marathon/

Traffic impacts:

  • Northbound US 51 is open to two lanes. Motorists can expect lane closures and speed reductions.
  • Southbound US 51 is open to two lanes. The speed limit is 55 MPH through the work zone.
  • County WW, under the US 51 bridge, is open to traffic. Motorists may encounter flagging operations. The speed limit is 35 mph and there is an 11-foot width restriction.

 

Portage County

 

Highway: WIS 34

Location: Between Junction City and Knowlton (Marathon County)

Schedule: August 21 to mid-December 2017

Cost: $1.2 million

Description: Crews will remove deteriorated concrete from the bridge piers. New concrete will be placed around the piers to protect the reinforcing steel and steel piling.

Traffic impacts: WIS 34 will remain open to traffic during construction. Motorists can expect some lane closures and flagging operations. Most of the work will be done under the bridge. Boaters using the river at this location are asked to use caution when navigating through this location.

 

Highway: I-39 northbound (*updated*)

Location: Waushara County O to WIS 54 (Plover)

Schedule: August 7 to May 2018

Cost: $3.2 million

Description: Crews will mill the pavement and overlay the surface with asphalt. Work includes paving the ramps at WIS 73, County D and County W. Crews will also install ramp gates at the interchange entrance ramps to I-39.

Traffic impacts: Northbound motorists can expect to encounter weekday lane closures and speed reductions. Almost all work for this year will be done by October 13. Additional pavement operations are scheduled to take place in spring 2018.

 

Price County

 

Highway: WIS 111 (*updated*)

Location: Between WIS 13 and US 8

Schedule: September 11 to October 20, 2017

Cost: $420,000

Description: Crews will replace the bridge over Needle Creek.

Traffic impacts: WIS 111 is closed and detoured via US 8 and WIS 13.

 

Highway: WIS 86

Location: Between WIS 13 and County G, in Ogema

Schedule: August 21 to October 13, 2017

Cost: $423,000

Description: Crews will replace the current pipe culvert at Holmes Creek with a concrete box culvert.

Traffic impacts: WIS 86 will be closed at Holmes Creek during construction. Traffic is detoured via WIS 13 and County G.

 

Highway: WIS 182 (*updated*)

Location: WIS 13 to Saunders Avenue and the Flambeau River bridge, in Park Falls

Schedule: May 22 to early November 2017

Cost: $2.8 million

Description: Crews will replace the bridge over the North Fork of the Flambeau River. Improvements include resurfacing WIS 182 between WIS 13 and Saunders Avenue.

Website: https://projects.511wi.gov/wis182/

Traffic impacts: The bridge is closed. Traffic is detoured via WIS 13, WIS 70 and WIS 47.

 

Shawano County

 

Highway: WIS 52

Location: Wausau to Aniwa

Schedule: June 26 to October 25, 2017

Cost: $1.6 million

Description: Crews will mill and pave the highway from Elm Road to the Eau Claire River.

Website: https://projects.511wi.gov/wis52marathon/

Traffic impacts:

  • Motorists can expect to encounter daytime lane closures and flagging operations.
  • Motorists are reminded to drive with caution as they approach the work site. Watch for turning and/or slow moving trucks or equipment.

 

Vilas County

 

Highway: WIS 47 (*updated*)

Location: Between Lower Sugar Bush Lane and US 51

Schedule: September 5 to October 31, 2017

Cost: $1.4 million

Description: Improvements include resurfacing the highway and replacing several culverts.

Traffic impacts: WIS 47 will remain open to traffic during construction. Motorists can expect lane closures and flagging operations.

 

Waupaca County

 

Highway: WIS 22

Location: 13th Street to WIS 156, Clintonville

Schedule: March 20 to late October 2017

Cost: $4.5 million

Description: Crews will reconstruct the highway. Other improvements include: new sidewalks, curb and gutter, and street lighting. Some modifications will be made to the WIS 22/156 intersection to improve safety.

Website: https://projects.511wi.gov/wis22clintonville/

Traffic impacts: WIS 22 is closed between 13th Street and WIS 156. Through traffic is detoured via 7th Street, N. Lyon Street, E. 12th Street, SSGT Warren Hansen Drive and WIS 156.

 

Waushara County

 

Highway: I-39 northbound (*updated*)

Location: Waushara County O to WIS 54 (Plover)

Schedule: August 7 to May 2018

Cost: $3.2 million

Description: Crews will mill the pavement and overlay the surface with asphalt. Work includes paving the ramps at WIS 73, County D and County W. Crews will also install ramp gates at the interchange entrance ramps to I-39.

Traffic impacts: Northbound motorists can expect to encounter weekday lane closures and speed reductions. Almost all work for this year will be done by October 13. Additional pavement operations are scheduled to take place in spring 2018.

 

Highway: I-39

Location: Coloma to Plainfield

Schedule: May 15 to May 2018

Cost: $1.4 million

Description: Crews will place concrete deck overlays and replace the approaches to five bridges located along I-39, including the north and southbound bridges at the WIS 73 interchange.

Traffic impacts: Motorists can expect speed reductions and 14-foot width restrictions on I-39 at the WIS 73 interchange in Plainfield.

 

Wood County

 

Highway: WIS 54 (*updated*)

Location: Lonesome Road to School Road

Schedule: March 20 to October 20, 2017

Cost: $2.6 million

Description: Crews will reconstruct the highway on new alignments (between the intersections of Lonesome Road and Smith Lane and at Wood County D) to straighten horizontal curves and improve safety. Other improvements include: installing centerline rumble strips, constructing wider driving lanes with paved shoulders, and improving pavement drainage.

Website: https://projects.511wi.gov/wis54wood/

Traffic impacts: WIS 54 is closed between Smith Lane and Lonesome Road until October 20, 2017. Traffic is detoured via WIS 80, WIS 173, and WIS 73.

 

 

Schedules are subject to change and are dependent on favorable weather conditions and construction progress.

Previous Article

Mortar & Pestle opens doors to new ...

Next Article

Kenton Lee Kramer, 68

Related articles More from author

  • EducationGovernmentLocalLocal Interest

    Unified School District of Antigo Committee of the Whole Meeting Agenda for 5/11/21

    May 8, 2021
    By Antigo Times
  • News

    Dear Monty: Five tips to buy and share a personal residence

    February 27, 2018
    By Antigo Times
  • LocalLocal InterestSports

    New Antigo Head Boys Varsity Baseball Coach-Alex Heiny

    August 25, 2020
    By Antigo Times
  • DOTLocal InterestNews

    North Central Region Road Construction Update

    July 6, 2017
    By Antigo Times
  • HealthNews

    Renewing disabled parking cards made easier

    April 15, 2015
    By Antigo Times
  • GovernmentHealthLocal InterestNews

    Governor Evers Makes Historic Investments in Health Care Coverage and Access

    March 15, 2019
    By Antigo Times

Leave a reply Cancel reply

Timeline

  • May 17, 2022

    T.J.Maxx to Open in Antigo

  • May 17, 2022

    Antigo Tennis Tournament in Wausau

  • May 16, 2022

    Very High Fire Danger Across Most Of Wisconsin

  • May 16, 2022

    Rise in COVID-19 Cases Calls for Increased Precautions to Protect Health Statewide

  • May 16, 2022

    Near Critical Fire Danger Across Northwest Wisconsin

Copyright © 2020 Multi Media Channels LLC.
All Rights Reserved. No part of this publication or any of its contents may be reproduced, copied, modified or adapted without the prior written consent of Multi Media Channels LLC.
×