The Wisconsin Department of Transportation (WisDOT) provides a weekly update on road construction in North Central Wisconsin, which includes: Adams, Green Lake, Florence, Forest, Iron, Langlade, Lincoln, Marathon, Marquette, Menominee, Oneida, Portage, Price, Shawano, Vilas, Waupaca, Waushara, and Wood counties.
To learn more about North Central Region transportation news, project updates, studies, and more:
Adams County
Highway: WIS 13
Location: County E to the railroad crossing (Adams)
Schedule: August 15 to mid-September 2016
Cost: $524,000
Description: Crews will resurface the roadway, install centerline rumble strips, and reconstruct the railroad crossing.
Website: http://projects.511wi.gov/wis13adams/
Traffic impacts: Crews will close WIS 13 to through traffic between Adams County F and County M at 6 a.m. on Monday, August 22. Traffic will be detoured via County F, County Z, and County J. Local traffic should expect to encounter flagging operations. The road is scheduled to reopen before the end of the day on Friday, August 26
Iron County
Highway: WIS 182
Location: Bear River Bridge; Price County line to WIS 47
Schedule: June 13, 2016 to late October 2016
Cost: $3.6 million
Description: Crews will replace the Bear River Bridge, resurface the roadway, replace 18 culverts, and install centerline rumble strips.
Website: http://projects.511wi.gov/182iron/
Traffic impacts: Single lane closures, temporary traffic signals, and a reduced lane width of 13 feet at the Bear River Bridge.
Langlade County
Highway: WIS 55 (*added*)
Location: School Road to County T
Schedule: August 22 to late October 2016
Cost: $1.46 million
Description: Crews will resurface the roadway, replace four culverts and install centerline rumble strips.
Website: http://projects.511wi.gov/wis55langlade/
Traffic impacts: Motorists can expect to daytime, single lane closures and flagging operations.
Highway: WIS 55
Location: WIS 64 to Hollister Road
Schedule: August 8 to early September 2016
Cost: $1.15 million
Description: Crews will resurface the roadway.
Website: http://projects.511wi.gov/wis55langlade/
Traffic impacts: Motorists can expect to encounter lane shifts, single lane closures, and flagging operations.
Highway: WIS 55
Location: South Langlade County line to WIS 64
Schedule: July 11 to early September 2016
Cost: $1.15 million
Description: Crews will resurface the roadway, replace three deteriorating culverts, and install centerline rumble strips.
Website: http://projects.511wi.gov/wis55langlade/
Traffic impacts: Motorists can expect to encounter single lane closures and flagging operations.
Marathon County
Highway: WIS 29
Location: County J to County Q
Schedule: August 2 to late October 2016
Cost: $2.65 million
Description: Crews will repair and replace pavement on WIS 29 and the two interchange ramps, resurface the interchange bridges, and reconstruct the median crossovers.
Website: http://projects.511wi.gov/29marathon/
Traffic impacts: Motorists can expect to encounter single lane closures and a reduced speed limit of 55 MPH.
Highway: WIS 52 (Stewart Avenue and Scott Street) (*updated*)
Location: 17th Avenue to 1st Street, WIS 52/Stewart Avenue/WIS 29 interchange ramps
Schedule: June 29, 2016 to late October 2016
Cost: $3.25 million
Description: Crews will resurface and recondition sections of the roadway, replace pavement, and replace traffic signals. Additional improvements include new sections of curb and gutter, sidewalk and storm sewer
Website: http://projects.511wi.gov/stewartave/
Traffic impacts:
Highway: US 51
Location: Decator Drive to the Lincoln County line
Schedule: July 5, 2016 to late May 2017
Cost: $4.5 million
Description: Crews will resurface the highway and the four County WW ramps to extend the life of the pavement.
Website: http://projects.511wi.gov/us51marathon/
Traffic impacts: Motorists can expect to encounter single lane closures and a reduced speed limit of 55 MPH.
Highway: US 51
Location: Decator Drive to County WW
Schedule: February 29, 2016 to late October 2017
Cost: $6.32 million
Description: Crews will replace the bridge decks on northbound US 51 over Decator Drive and on northbound and southbound US 51 over County WW
Website: http://projects.511wi.gov/51bridgesmarathon/
Traffic impacts:
Highway: WIS 29
Location: Sunrise Drive to Business 51
Schedule: April 29, 2014 to May 25, 2017
Cost: $18.8 million
Description: Crews will widen and replace bridge decks on WIS 29 bridges over Business 51 and the Wisconsin River.
Website: http://projects.511wi.gov/wis29/
Traffic impacts:
Marquette County
Highway: I-39 (*updated*)
Location: WIS 23/82 to Edgewood Court
Schedule: March 14, 2016 to May 15, 2017
Cost: $7.2 million
Description: Crews will replace the I-39 southbound bridge and resurface the I-39 northbound bridge over the WIS 23/82 interchange, realign the southbound ramps at the interchange, realign a section of Crossroads Clinic Road, resurface the northbound and southbound I-39 bridges over Fawn Court, and raise the County M and Edgewood court bridges over I-39.
Website: http://projects.511wi.gov/i39-marquette/
Traffic impacts:
Oneida County
Highway: US 8 (*added*)
Location: US 8/WIS 17 and US 8/County G intersections
Schedule: August 25 to early October 2016
Cost: $424,000
Description: Crews will resurface the intersections and replace traffic signal detector loops.
Website: http://projects.511wi.gov/us8-oneida/
Traffic impacts: Motorists can expect to encounter single lane closures and flagging operations at the intersections.
Highway: US 51 (*updated*)
Location: Bearskin Trail Bridge, Hazelhurst
Schedule: April 11, 2016 to early October 2016
Cost: $1.2 million
Description: Crews will replace the existing bridge to meet current standards.
Website: http://projects.511wi.gov/51bearskin/
Traffic impacts: Motorists can expect to encounter weekday single lane closures and temporary traffic signals at the bridge until August 19.
Highway: US 51
Location: Rocky Run Road to County Y
Schedule: February 29, 2016 to November 2017
Cost: $10.1 million
Description: Crews will reconstruct US 51, replace culverts, reconstruct intersections, lengthen existing passing lanes, and construct a new bridge over Rocky Run Creek.
Website: http://projects.511wi.gov/us51oneida/
Traffic impacts: The northbound and southbound passing lanes between Rocky Run Road and South Blue Lake Road are closed. US 51 remains open to one lane of traffic in each direction.
Portage County
Highway: WIS 54 (*updated*)
Location: WIS 54/Wood and Portage County U intersection
Schedule: June 10 to early September 2016
Cost: $1.5 million
Description: Crews will reconstruct the intersection as a J-turn to improve safety.
Website: http://projects.511wi.gov/54countyu/
Traffic impacts:
Highway: WIS 49, town of Alban
Location: Cedar Road to Lake View Road
Schedule: May 16, 2016 to September 2, 2016
Cost: $261,000
Description: Crews will rout and seal cracks to help prevent further pavement deterioration and chip seal and fog seal the highway surface to improve ride quality and protect the asphalt.
Website: http://projects.511wi.gov/wis49portage/
Traffic impacts:
Highway: I-39
Location: WIS 66/Stanley Street (Stevens Point) to the Little Plover River (Plover)
Schedule: April 4, 2016 to late October 2016
Cost: $1.5 million
Description: Crews will resurface the northbound and southbound bridges on I-39 over WIS 66/Stanley Street, over the railroad, and over the Little Plover River.
Website: http://projects.511wi.gov/i39stanley/
Traffic impacts: Work is suspended and is currently scheduled to resume August 29.
Highway: Business 51 (Post Road), Plover (*updated*)
Location: Green Drive to Springville Drive
Schedule: March 7, 2016 to late November 2016
Cost: $8.65 million
Description: Crews will convert the existing, undivided four-lane roadway to a divided four-lane roadway with wider lanes, a raised median, and designated turn lanes. Work also includes constructing new sidewalks, bicycle lanes, and providing new street lighting.
Website: http://projects.511wi.gov/business51/
Traffic impacts:
Shawano County
Highway: WIS 29
Location: US 45/WIS 29 and WIS 29/47 interchanges
Schedule: August 15 to late October 2016
Cost: $2.7 million
Description: Crews will resurface the ramps and roadways at the interchanges and apply anti-skid treatment to the bridges over WIS 29.
Website: http://projects.511wi.gov/wis29shawano/
Traffic impacts:
Highway: WIS 47 (Airport Drive)
Location: WIS 29 to WIS 22 (Green Bay Street), Shawano
Schedule: August 1 to late October 2016
Cost: $2.6 million
Description: Crews will reconstruct WIS 47 as a two-lane road between County B and WIS 22. Crews will also resurface sections of the roadway, improve intersections, and reconstruct the railroad crossing.
Website: http://projects.511wi.gov/47shawano/
Traffic impacts:
Highway: WIS 29
Location: Embarrass River Bridge
Schedule: June 13 to mid-October 2016
Cost: $1.53 million
Description: Crews will replace the bridge.
Website: http://projects.511wi.gov/29embarrass/
Traffic impacts: Motorists can expect to encounter single lane closures and a reduced speed limit of 55 MPH in both directions between Seneca Road and Fink Road.
Waupaca County
Highway: US 45 (*added*)
Location: County W to County D
Schedule: August 22 to mid-September 2016
Cost: $750,000
Description: Crews will resurface the roadway.
Website: http://projects.511wi.gov/us45waupaca/
Traffic impacts:
Highway: WIS 54 (*updated*)
Location: Royalton railroad overpass to Jeanne Street, New London
Schedule: July 11 to early September 2016
Cost: $1.54 million
Description: Crews will resurface the roadway, install centerline and shoulder rumble strips, replace three culverts, complete maintenance on four culverts, and upgrade beam guard.
Website: http://projects.511wi.gov/wis54waupaca/
Traffic impacts: Motorists can expect to encounter daytime single lane closures and flagging operations.
Wood County
Highway: WIS 54 (*updated*)
Location: WIS 54/Wood and Portage County U intersection
Schedule: June 10 to early September 2016
Cost: $1.5 million
Description: Crews will reconstruct the intersection as a J-turn to improve safety.
Website: http://projects.511wi.gov/54countyu/
Traffic impacts:
Highway: County P (Old US 10), Auburndale
Location: US 10 to County F
Schedule: April 25, 2016 to late November 2016
Cost: $5.5 million
Description: Crews will replace pavement, construct a new local road system, remove railroad crossings, reconstruct and realign intersections, and construct a pedestrian underpass.
Website: http://projects.511wi.gov/us10auburndale/
Traffic impacts:
Motorists are reminded to drive with caution in the work zone and should be prepared to encounter slow moving trucks. Motorists should slow down, use caution and stay alert when driving through construction zones. To avoid delays, consider taking an alternative route and avoid peak travel periods.
Construction-related traffic impacts are subject to change and are dependent on favorable weather conditions and construction status.