The Wisconsin Department of Transportation (WisDOT) provides a weekly update on road construction in north central Wisconsin, which includes: Adams, Green Lake, Florence, Forest, Iron, Langlade, Lincoln, Marathon, Marquette, Menominee, Oneida, Portage, Price, Shawano, Vilas, Waupaca, Waushara, and Wood counties.
To learn more about North Central Region transportation news, project updates, studies, and more:
Marathon County
Highway: US 51
Location: Marathon County WW interchange
Schedule: February 29, 2016 to late October 2017
Cost: $6.32 million
Description: Last year crews replaced the bridge decks on northbound US 51 over Decator Drive and constructed a temporary structure for traffic management. This year crews will replace the bridge decks on northbound and southbound US 51 over County WW
Website: https://projects.511wi.gov/us51marathon/
Traffic impacts:
Marquette County
Highway: I-39 (*updated*)
Location: WIS 23/82 to Edgewood Court
Schedule: March 14, 2016 to May 19, 2017
Cost: $7.2 million
Description: Crews will replace the I-39 southbound bridge and resurface the I-39 northbound bridge over the WIS 23/82 interchange, realign the southbound ramps at the interchange, realign a section of Crossroads Clinic Road, resurface the northbound and southbound I-39 bridges over Fawn Court, and raise the County M and Edgewood court bridges over I-39.
Website: http://projects.511wi.gov/i39-marquette/
Traffic impacts: Beginning April 26, motorists can expect weekday, single lane closures on I-39 at the WIS 23/82 interchange.
Oneida County
Highway: US 51
Location: Rocky Run Road to County Y
Schedule: February 29, 2016 to early July 2017
Cost: $10.1 million
Description: Crews will reconstruct US 51, replace culverts, reconstruct intersections, lengthen existing passing lanes, and construct a new bridge over Rocky Run Creek.
Website: http://projects.511wi.gov/us51oneida/
Traffic impacts:
Portage County
Highway: I-39
Location: Plainfield to Stevens Point
Schedule: April 17 to mid-August 2017
Cost: $1.4 million
Description: Crews will paint the beams of five bridges over I-39.
Traffic impacts: Motorists will encounter lane closures and speed reductions.
Highway: I-39
Location: North of the County D interchange (Almond)
Schedule: April 17 to mid-August 2017
Cost: $1.1 million
Description: Crews are replacing a culvert.
Traffic impacts: Motorists will encounter lane closures and speed reductions.
Price County
Highway: US 8 (*added*)
Location: Miller Road (Prentice) to Lustila Road (Brantwood)
Schedule: April 26 to mid-July 2017
Cost: $2.7 million
Description: Crews will resurface the highway, install centerline rumble strips, replace approaches to a bridge located over railroad tracks, reconfigure lanes at the interchange with WIS 13, and replace or repair 26 culverts.
Traffic impacts: Motorists can expect to encounter lane closures and temporary traffic signals.
Shawano County
Highway: WIS 29
Location: Between Shawano County OO and River Road
Schedule: April 10 to late July 2017
Cost: $1.2 million
Description: Crews will repair nine bridge decks, improve bridge approaches and shoulders, and apply a polymer overlay to the decks to increase friction and improve safety
Traffic impacts: Motorists can expect to encounter single lane closures.
Waupaca County
Highway: WIS 22 (*updated*)
Location: 13th Street to WIS 156, Clintonville
Schedule: March 20 to late October 2017
Cost: $4.5 million
Description: Crews will reconstruct the highway. Other improvements include: new sidewalks, curb and gutter, and street lighting. Some modifications will be made to the WIS 22/156 intersection to improve safety.
Website: https://projects.511wi.gov/wis22clintonville/
Traffic impacts:
Wood County
Highway: WIS 54 (*updated*)
Location: Lonesome Road to School Road
Schedule: March 20 to August 31, 2017
Cost: $2.6 million
Description: Crews will reconstruct the highway on new alignments (between the intersections of Lonesome Road and Smith Lane and at Wood County D) to straighten horizontal curves and improve safety. Other improvements include: installing centerline rumble strips, constructing wider driving lanes with paved shoulders, and improving pavement drainage.
Website: https://projects.511wi.gov/wis54wood/
Traffic impacts:
Highway: County P (Old US 10), Auburndale
Location: US 10 to County F
Schedule: April 25 to early June 2016
Cost: $5.5 million
Description: Crews will replace pavement, construct a new local road system, remove railroad crossings, reconstruct and realign intersections, and construct a pedestrian underpass.
Website: http://projects.511wi.gov/us10auburndale/
Traffic impacts: Kennedy Street is closed between Marshfield Street and Van Avenue.
Motorists are reminded to drive with caution in the work zone and should be prepared to encounter slow moving or merging vehicles. Pay attention to speed limits and remember that using handheld cell phones in Wisconsin work zones is illegal. To avoid delays, consider taking an alternative route and avoid peak travel periods.
All construction-related traffic impacts are subject to change and are dependent on favorable weather conditions and construction status