The Wisconsin Department of Transportation (WisDOT) North Central Region provides weekly road construction updates for the following counties in North Central Wisconsin: Adams, Green Lake, Florence, Forest, Iron, Langlade, Lincoln, Marathon, Marquette, Menominee, Oneida, Portage, Price, Shawano, Vilas, Waupaca, Waushara, and Wood counties.
Construction schedules may fluctuate pending favorable weather conditions and crew availability. This update can be found at: https://projects.511wi.gov/weeklyupdates-nc/
Regionwide projects are designed to complete similar work types at multiple locations in multiple counties. This allows for the project to be administered and constructed efficiently, under a single contract, rather than several smaller contracts. Information on those projects and their impacts to traffic can be found here: http://projects.511wi.gov/region-wide-nc/
Adams County
Highway: WIS 82
Location: County B to the Marquette County line
Schedule: April 12, 2021 with anticipated completion of June 30, 2021
Project ID: 1430-01-87
Work scheduled: Crews will work on grading, shoulders, and guardrails once asphalt is completed on June 24. Paving marking will follow with punch list and cleanup items next week.
Traffic impacts: WIS 82 is closed from the Marquette/Adams County Line to County B. Local traffic and EMS access is maintained while final items of the project are completed. The entire project length is currently accessible on concrete pavement in both lanes. Pending favorable weather, crews anticipate project completion and roadway opening on June 30.
Website: https://projects.511wi.gov/wis82-cth-b-marquette/
Highway: WIS 82
Location: WIS 13 to County B
Schedule: April 12, 2021 to October 2021
Project ID: 1430-01-77
Work scheduled for next week: Crews will work on grading.
Traffic impacts: WIS 82 is closed. Traffic is detoured via WIS 13, WIS 23, and I-39. Access to residents and businesses along the corridor will be maintained throughout the project.
Website: https://projects.511wi.gov/wis82-cth-b-wis13/
Iron County
Highway: US 51/US 2
Location: US 2 from State Line Road in town of Kimball to the Michigan State line and US 51 from the rest stop in Hurley through the intersection with US 2
Schedule: May 3, 2021 to October 28, 2021
Project ID: 1175-21-71
Description: The project includes removing the existing US 51 overhead structure and replacing the interchange with a single lane roundabout with bypass lanes.
Work scheduled for next week: Crews will place erosion control, install storm sewer, and remove pavement on ramps and place gravel on US 2.
Traffic impacts for next week:
Website: https://projects.511wi.gov/us251rab/
Highway: US 2
Location: County B to the Michigan state line (adjacent to the roundabout project)
Schedule: June 7 to July 26, 2021
Project ID: 1185-03-71
Description: Two inches of pavement will be removed and replaced. Existing guardrail at the box culvert over the West Fork Montreal River will be replaced along with one culvert.
Work scheduled for next week: Crews will continue pavement removal and replacement.
Traffic impacts for next week: Motorists will encounter flagging operations.
Website: https://projects.511wi.gov/us2resurface/
Langlade County
Highway: WIS 64/WIS 52
Location: From US 45 in Antigo to Clover Road in Antigo and the bridge over Spring Brook near Hafemeister Lane
Schedule: May 24, 2021 to October 31, 2021
Project ID: 9140-12-70/73
Project description: This project will remove and replace two inches of asphalt pavement on WIS 64 from US 45 to Clover Road. The bridge over Spring Brook will be replaced half at a time.
Work scheduled for next week: Crews will be excavating, install piling, forming the east wall, backfill and other work on the structure.
Overall traffic impacts: WIS 64/WIS 52 traffic is restricted to a single lane with temporary signals at Spring Brook bridge. Traffic will utilize the westbound lane through the work zone. WIS 64/WIS 52 traffic will maintain a minimum 10-foot-wide lane during construction.
Marathon County
Highway: Business 51
Location: (Grand Avenue) WI Central Ltd. Railroad Bridge, Wausau
Schedule: June 7 to September 13, 2021
Project ID: 6999-03-63
Work scheduled for next week: Crews will pour concrete on June 23, let it cure over the weekend, clean up the site, and pave bridge approaches.
Traffic impacts: A maximum width of 13-feet applies. Traffic is maintained on a single lane in each direction with traffic shifted to the east side of the bridge.
Website: https://projects.511wi.gov/wis52bus51wausau/
Menominee County
Highway: WIS 47
Location: Duquaine Road (BIA 334) to North Junction County VV and the bridge over the Wolf River
Schedule: April 12, 2021 to November 2021
Project ID: 9650-17-61/70
Work scheduled for next week:
Traffic impacts:
Website: https://projects.511wi.gov/wis47menominee/
Oneida County
Highway: WIS 70
Location: Morgan Road to US 51, Minocqua
Project ID: 9070-05-73
Schedule: June 16, 2021 to August 2021
Description: The existing pavement will be removed and replaced with new asphalt pavement. Curb ramps will be replaced and upgraded to meet current Americans with Disabilities Act (ADA) standards. Spot repairs will be made to the existing curb & gutter, traffic signals, and inlets. Signs will be replaced. Thermoplastic will be added at two snowmobile crossings.
Work scheduled: Pavement removal and replacement on the inside lanes and two-way-left-turn-lane. Crews will also install new traffic signal detectors.
Traffic Impacts: Single lane closures in each direction.
Website: https://projects.511wi.gov/wis70oneida/
Oneida and Vilas Counties
Highway: WIS 17
Location: Pollyanna Road to WIS 70
Schedule: April 26, 2021 to July 9, 2021
Project ID: 9040-02-61/62
Work scheduled for next week: Crews will be paving intersections, install pavement marking, and work on shoulders.
Traffic impacts: Traffic will be reduced to a single lane with flaggers during pavement removal and replacement, and shoulder work.
Portage County
Highway: Business 51 (Post Road)
Location: Springville Drive to Tommy’s Turnpike
Schedule: April 2021 through October 2022
Project ID: 6414-00-79
Work scheduled for next week:
Traffic impacts:
Website: https://projects.511wi.gov/business51/
Shawano County
Highway: WIS 29 (NEW)
Location: County U intersection, town of Herman
Schedule: June 28, 2021 to October 14, 2021
Project ID: 1058-02-73
Work scheduled for next week: Crews will set up temporary traffic control and erosion control. Crews will begin grading within the median and County U intersection.
Traffic impacts: Temporary speed reduction of 55 mph applies. On Monday, June 28, the left lanes on WIS 29 eastbound and westbound will be closed. The lanes will reopen prior to the holiday weekend. County U south intersection will be closed to through traffic until July 23. Shawano County Highway Department will be posting a detour for the County U closure.
Website: https://projects.511wi.gov/wis29countyu/
Waushara County
Highway: WIS 21/WIS 22/WIS 73
Location: Between Plainfield and Wautoma
Schedule: June 14, 2021 to August 20, 2021
Project ID: 6170-00-61/6310-00-60/6321-00-72
Work scheduled for next week: Crews will continue removal and replacement of curb and gutter and sidewalk, perform grading, continue installing culvert pipes at two cattle passes, and install two new cross culverts on WIS 73.
Traffic impacts: WIS 73, WIS 21, and WIS 22 are open during construction. Motorists can expect multiple single lane closures with flagging operations during daytime hours along with various shoulder and single lane closures.
Highway: WIS 22
Location: Marquette County line/County JJ in the town of Dakota to WIS 21 West/West Division Street in the city of Wautoma
Schedule: May 24, 2021 to July 15, 2021
Project ID: 6150-00-72
Work scheduled for next week: Crews will continue pavement removal and replacement.
Traffic impacts: Daily flagging during pavement removal and replacement. Temporary pavement markings will be installed at the end of each day during paving, slower moving vehicles will be in the are during that work.
Website: https://projects.511wi.gov/wis22resurface/
Highway: WIS 73
Location: From 4th Court to 5th Avenue in the town of Plainfield and the WIS 73 ramps to and from I-39
Schedule: April 12, 2021 to August 27, 2021
Project ID: 1160-00-79/6321-00-71
Work scheduled for next week: Crews will continue concrete removal along northbound WIS 73.
Traffic impacts: Traffic has been shifted onto the new southbound lanes and temporary widenings. A 12-foot width restriction remains in place.
For more information regarding traffic impacts, transportation news and improvement project updates in Wisconsin’s North Central region:
Comments
No comments on this item Please log in to comment by clicking here