The Wisconsin Department of Transportation (WisDOT) North Central Region provides weekly road construction updates for the following counties in North Central Wisconsin: Adams, Green Lake, Florence, Forest, Iron, Langlade, Lincoln, Marathon, Marquette, Menominee, Oneida, Portage, Price, Shawano, Vilas, Waupaca, Waushara, and Wood counties.
Construction schedules may fluctuate pending favorable weather conditions and crew availability. This update can be found at: https://projects.511wi.gov/weeklyupdates-nc/
Adams County
Highway: WIS 82
Location: WIS 13 to County B
Schedule: April 12, 2021 to late October 2021
Project ID: 1430-01-77
Work scheduled for next week: Concrete grinding will continue and install pavement markings.
Traffic impacts: WIS 82 remains closed to thru traffic. A posted detour via WIS 13, WIS 23, and I-39 is in place. Access to residents and businesses along the corridor will be maintained throughout the project.
Website: https://projects.511wi.gov/wis82-cth-b-wis13/
Highway: WIS 13
Location: Bridges over Little Roche a Cri and Carter Creek
Schedule: This project is complete.
Project ID: 6140-01-65
Work scheduled for next week: Crews will work on final clean up.
Traffic impacts: None.
Florence County
Highway: WIS 139
Location: Between the Forest County line and Fay Lake Road
Schedule: September 7, 2021 to October 2021
Project ID: 9110-72-10
Work scheduled for next week: Crews will place gravel shoulders and install final pavement markings.
Traffic impacts: Flagging operations during daylight working hours will be utilized to restrict traffic to one travel lane when needed. Slight delays are anticipated.
Forest County
Highway: WIS 32
Location: Forest Avenue in Wabeno to US 8 in Laona
Schedule: This project is complete.
Forest and Florence Counties
Highway: WIS 101
Location: From US 8 in Armstrong Creek to Woods Creek Road in Fern
Schedule: August 9, 2021 to October 29, 2021
Project ID: 9304-11-70/9304-12-70
Work scheduled for next week: Crews will work on pavement markings and work on final clean up.
Traffic impacts: WIS 101 is open. Traffic will be reduced to a single lane with flaggers during pavement markings and final clean up.
Iron County
Highway: US 51/US 2
Location: US 2 from State Line Road in town of Kimball to the Michigan State line and US 51 from the rest stop in Hurley through the intersection with US 2
Schedule: May 3, 2021 to October 28, 2021
Project ID: 1175-21-71
Work scheduled for next week: Crews will complete removal of temporary roadways, place topsoil and gravel shoulders, install rumble strips, signs, and pavement markings.
Traffic impacts: All directions are utilizing the roundabout. Motorists may encounter flagging operations. Traffic may encounter flaggers. All roadways are anticipated to be open next week.
Website: https://projects.511wi.gov/us251rab/
Langlade County
Highway: WIS 64/WIS 52
Location: From US 45 in Antigo to Clover Road in Antigo and the bridge over Spring Brook near Hafemeister Lane
Schedule: This project is complete.
Project ID: 9140-12-70/73
Highway: WIS 64
Location: County P to the Oconto County line and bridge over Wolf River in Langlade
Schedule: July 28, 2021 to October 2021
Project ID: 9140-12-71/74
Work scheduled for next week: Shoulder work will finish up early in the week. Centerline rumble strips and pavement markings will be installed. Thermoplastic snowmobile crossings will be installed at three locations.
Traffic impacts: Flagging operations from WIS 55 to the Oconto County line.
Lincoln County
Highway: US 51
Location: From the Marathon/Lincoln County line in Pine River to County K (Exit 211) in Merrill
Schedule: July 19, 2021 to November 15, 2022
Project ID: 1176-22-72/73
Work scheduled for next week: Paving crews will continue from the Wisconsin River to the southern project limits and pave the southbound County Q on and off ramps. Towards the end of the week, crews will begin placing new pavement markings.
Traffic impacts:
Website: https://projects.511wi.gov/us51nbsb/
Highway: US 51/County Q Bridge
Location: County Q bridge over US 51, Exit 205, Merrill
Schedule: August 9, 2021 to October 29, 2021
Project ID: 1176-22-60
Work scheduled for next week: Crews will install concrete pavement and install curb and gutter.
Traffic impacts: County Q is down to a single lane. Motorists using the US 51 off ramps and County Q will encounter temporary traffic signals. Traffic will be switched to the southern lane.
Menominee County
Highway: WIS 47
Location: Duquaine Road (BIA 334) to North Junction County VV and the bridge over the Wolf River
Schedule: April 12, 2021 to November 2021
Project ID: 9650-17-61/70
Work scheduled for next week: Crews will place gravel shoulders between County VV (east) and County VV (west), remove and replace beam guard on WIS 47 south near Wolf River Drive, finish topsoil and gravel driveways, and finish pavement markings.
Traffic impacts: Motorists can expect flagging operations between Fairgrounds Road and County VV (west)
Website: https://projects.511wi.gov/wis47menominee/
Oneida County
Highway: US 51
Location: Bearskin Bridge to Rocky Run Road
Schedule: October 4, 2021 to week of October 29, 2021
Project ID: 1170-16-71
Work scheduled for next week: Crews plan to complete pavement markings, centerline rumble strips, and snowmobile crossings.
Traffic impacts: One lane of US 51 is closed with traffic routed through the construction area by flaggers. Motorists should expect some delays.
Portage County
Highway: Business 51 (Post Road)
Location: Springville Drive to Tommy’s Turnpike
Schedule: April 2021 through October 2022
Project ID: 6414-00-79
Work scheduled for next week:
Traffic impacts:
Website: https://projects.511wi.gov/business51/
Highway: I-39
Location: I-39/Portage County B interchange
Schedule: October 11-12, 2021; March 2022 – June 2022
Project ID: 1166-12-89
2021:
2022:
Website: https://projects.511wi.gov/i39countyb/
Shawano County
Highway: WIS 29
Location: County U intersection, town of Herman
Schedule: This project is complete.
Project ID: 1058-02-73
Note: More information on how to navigate a J-Turn can be found on the project website: https://projects.511wi.gov/wis29countyu/
Vilas County
Highway: US 51
Location: US 51 from Woodland Drive to Vilas County M, Arbor Vitae
Schedule: October 4, 2021 to November 5, 2021
Project ID: 1170-20-72
Work scheduled for next week: Crews plan to complete removing and replacing asphalt, work on gravel shoulders, and will install centerline rumble strips.
Traffic impacts: One lane of US 51 will be closed, and traffic will be routed through the construction area with flaggers. Motorists should expect some delays.
For more information regarding traffic impacts, transportation news and improvement project updates in Wisconsin’s North Central region: